Feed-in Tariff (FiT) annual levelisation invoices for 2018-19 were sent to suppliers on Monday 9 September, confirming and reconciling total scheme costs and FiT-liable and exempt electricity demand volumes for the year. Total generation payments made to FiT installations came to £1,408,981,588, with an additional £55,517,775 made in deemed export payments. It was confirmed that suppliers supplied a total of 276.6TWh of electricity in 2018-19, but that 9.8TWh will be exempt from scheme costs with the Guarantee of Origin import cap breached with 33.3mn presented. The outturn cost to the consumer was £5.60/MWh. Suppliers have until 23 September to make any necessary payments.